1. Do you have any feedback on our proposals for land south of Burnell Avenue, including changes to the outfall, intake, control building and other proposed permanent infrastructure in this area?
Whilst we are pleased to note that there will be a shorter connection to the Thames Lee tunnel and the groundwork plans for Ham playing fields have been discontinued, we are concerned about the more extensive impact on the residents and environment of Burnell Avenue.
We are pleased to note that the in-river outfall structure will offer some protection for migrating fish and look forward to the evidence in the Environmental Assessment. It will however require 14 maintenance hatches (up from 5) all 2m by 2m except for a huge one at the reception shaft which may be 3m by 4m.
It is surprising that you have only just realised that an underground pumping system will be required, resulting in having to move a shaft approximately 20m further back from the riverbank.
The proposed 7m by 10m control building looks hideous and completely out of keeping with this well-loved section of the Thames Path. Cladding and planting etc. will do little to disguise this fact. You acknowledge that these plans will be detrimental to the historic environment of the Riverside North Conservation Area.
2. Do you have any feedback on the changes to our construction proposals in the Burnell Avenue area, including changes to the draft Order limits at Beaufort Road, and our revised predictions for heavy goods vehicle movements and construction schedule for the Burnell Avenue site?
The proposed increase in heavy lorries from over 6,246 to around 14,000 will harm air quality as well as increasing levels of noise and traffic congestion. The threat of four years of construction work and a much bigger intake structure is understandably causing alarm amongst residents, and you acknowledge that there will be significant traffic at Beaufort Road, Burnell Avenue, Dysart Avenue and Dukes Avenue and these proposals could have significant effects on human health. We would like to see a full assessment of the impacts before 2027.
3. Do you have any views on the consultation materials, events, publicity or another aspect of our supplementary consultation?
The 20-page consultation booklet was clear and informative and the diagrams were useful.
It seems extraordinary that you are planning this without knowing the combined impacts of TDRA and the River Thames Scheme which could happen at the same time and that should be fully explored before the Environmental Assessment next year.
We see that you propose to move below ground equipment associated with the outfall structure 12m further back and that you hope to reduce the need to remove trees. The removal of any trees would of course result in a loss of habitat and increased carbon emissions. Extending the infrastructure a further 50m underground into Burnell Avenue Open Space compared to 2025 plans would also impact wildlife.